Calendars

A calendar defines which days are working days and how many hours a working day holds. The scheduling engine uses it to convert a task’s duration (expressed in working days) into real calendar dates — skipping weekends and holidays so your finish dates reflect actual availability.

SettingMeaning
Working daysWhich days of the week count as working (default Monday–Friday).
Hours per dayLength of a working day. Accepts fractions — set 6.0 for a six-hour day.
Time zoneThe zone the calendar’s dates are interpreted in (default UTC).
ExceptionsDate ranges that override the weekly pattern — public holidays, company shutdowns, or one-off non-working spans.

Because hours per day is a decimal, part-time and custom-hour teams are first-class: a calendar with a 6-hour day stretches the same task duration across more elapsed days than a standard 8-hour calendar.

A calendar attaches to a project — every task in that project schedules against it by default. A resource can carry its own calendar to model an individual’s availability (for example, someone who doesn’t work Fridays); where a resource has no calendar, the project’s calendar applies.

A project’s effective non-working time will be the overlay (union) of every calendar applied to it, not just a single calendar. A project will apply:

  • a base project calendar — the org standard work week and hours;
  • a reusable holidays calendar — public holidays, created once and applied to many projects; and
  • an optional workspace / shutdown calendar — for an org-wide winter shutdown.

A day counts as non-working if any applied calendar marks it so: the weekly patterns compose by intersection (a weekday is working only when every applied calendar treats it as working) and the holiday/shutdown exceptions compose by union. Because the overlay is a union, the order calendars appear in is a display grouping only — it never changes the computed schedule.

A Working calendars panel in Project Settings will let anyone with the Resource Manager (Scheduler) role or above apply and reorder a project’s calendars and preview the effective working time day-by-day — each non-working day showing which applied calendar blocked it. Reading the applied set and its preview will be open to any project member; changing it will require the Scheduler role, the same gate as editing the schedule.

Applying calendars to a project draws only on the shared calendar library — the same calendars managed below. Per-resource / PTO calendars that make a task’s duration depend on who is assigned, holiday-feed (iCal) import, and cross-program calendar governance are not part of this release.

Method & pathPurpose
GET /api/v1/projects/{id}/calendars/The calendars applied to a project (base + overlays)
PUT /api/v1/projects/{id}/calendars/Replace the applied set (base calendar + ordered overlays)
GET /api/v1/projects/{id}/calendars/preview/?start=&end=Per-day effective working time, with the source that blocked each non-working day

During the CPM forward and backward passes, non-working days — weekends, plus any day inside a calendar exception — are skipped entirely. A task with a 5-day duration starting on a Thursday finishes the following Wednesday on a Monday–Friday calendar, not the following Monday. Add a holiday exception in that span and the finish slides another day.

Calendars are managed via the REST API (a visual settings editor is planned):

Method & pathPurpose
GET /api/v1/calendars/List calendars
POST /api/v1/calendars/Create a calendar
GET /api/v1/calendars/{id}/Retrieve (with exceptions)
PATCH /api/v1/calendars/{id}/Update
DELETE /api/v1/calendars/{id}/Delete

Any authenticated user can read calendars; creating and editing them requires the Project Manager or Project Admin role on at least one project.

Exceptions — the holiday and shutdown date ranges that override a calendar’s weekly pattern — are managed through a nested sub-resource on the calendar. The exceptions sub-resource lands in 0.4.

Method & pathPurpose
GET /api/v1/calendars/{id}/exceptions/List a calendar’s exceptions
POST /api/v1/calendars/{id}/exceptions/Add an exception
GET /api/v1/calendars/{id}/exceptions/{exc_id}/Retrieve one exception
PATCH /api/v1/calendars/{id}/exceptions/{exc_id}/Edit an exception
DELETE /api/v1/calendars/{id}/exceptions/{exc_id}/Remove an exception

An exception carries a start date (exc_start), an end date (exc_end), and an optional description. Set exc_start equal to exc_end for a single non-working day; exc_end must fall on or after exc_start. Overlapping ranges are allowed — the scheduler treats their union as non-working.

The parent calendar is taken from the URL, never the request body: an exception always belongs to the calendar it was created under and cannot be reassigned. Any authenticated user can read exceptions; creating, editing, and deleting them requires the Project Manager or Project Admin role — the same gate as editing the calendar itself.

Adding, editing, or removing an exception recomputes every project scheduled against the calendar — whether the calendar is that project’s base or one of its overlays — so dependent task dates stay true to the new working time. The change also rides the calendar’s sync delta to offline clients, keeping critical-path math holiday-aware offline. (Offline recompute composes against a project’s base calendar only until the overlay set flows through the sync delta — a tracked follow-up; the server always computes against the full composed set.)