MS Project import & export
TruePPM treats Microsoft Project as a peer interchange format. You can:
- Create a new project from an MS Project file — fastest path for migrators.
- Import tasks into an existing project — refresh or land tasks alongside the existing record.
- Export any project back to MS Project XML — round-trip with another tool.
- Round-trip PERT three-point estimates for Monte Carlo.
- See the import history on a project’s Overview (“Imported from … on … by …”).
Two file formats are supported on import: human-readable .xml (MSPDI; always supported), and binary .mpp when the server has the optional MPXJ / Java toolchain installed. Export is always .xml.
This page is organized by what you want to do. Start with the in-app flow, drop down to the REST API when you need automation, then consult the field-coverage tables for round-trip semantics.
Create a project from a file
Section titled “Create a project from a file”The fastest path for migrating a schedule into TruePPM. Two entry points open the same dialog:
- Sidebar → New project → Import — for a standalone project you own.
- Program settings → Projects → Import project — to land the new project inside an existing program. Requires program Admin.
In the dialog:
- Pick a format. TruePPM is reserved for an upcoming native bundle and is currently disabled. MS Project is selected by default.
- Pick a file type.
.xmlis enabled;.mppand.mpxare visually present but disabled (see callout below). Click “How do I get an .xml file from MS Project?” for inline guidance — “In MS Project (desktop): File → Save As, choose XML Format (.xml), then Save.”* - Drop the
.xmlfile on the dropzone (or click to browse) and confirm.
You’re navigated to the new project immediately. While the worker parses the file in the background, the project name is provisionally derived from the filename and the start date is today. Once the import finishes, both are overwritten from the file header and the schedule refreshes. The TopBar shows a quiet background-task indicator for the duration; a failed parse stays terminal — the project record remains so you can retry or delete it without losing the upload trail.
Import tasks into an existing project
Section titled “Import tasks into an existing project”Use this when the destination project already exists. From the project’s Schedule view:
- Open the Project actions (
···) overflow menu in the toolbar. - Choose Import from MS Project….
- Drop a
.xml(or.mpp, if the server supports it) file on the dropzone. - Confirm. The modal shows “Import started” and closes.
The import runs asynchronously — the worker parses the file in the background and the schedule refreshes once it finishes. There is no live per-import progress bar yet (#61).
Export a project
Section titled “Export a project”Open the Project actions (···) overflow menu in the Schedule view and choose Export to MS Project (.xml). The browser downloads the current schedule as MS Project XML 2003+. Export is allowed for any project member — Viewer role and above.
When the project has three-point estimates set on at least one work task, the export emits the standard PERT custom-field definitions and per-task values so the file round-trips with a .xml re-import (your own or another tool’s).
Project history
Section titled “Project history”After any file import (successful or failed), the project’s Overview page shows a Project history section listing recent imports — filename, when, who initiated it, status pill (Queued / Running / Complete / Failed), and tasks imported. The section is self-hiding: projects with no recorded imports don’t see an empty placeholder.
This is the recent-activity view, not a durable audit log. Rows are retained for 7 days (default TRUEPPM_IMPORT_RETENTION_DAYS), then purged. Long-lived audit retention lives on the enterprise overlay.
Reading the section requires Member+ on the project — Viewer role and above. Programmatic access is via GET /projects/{pk}/imports/.
Using the API
Section titled “Using the API”All operations authenticate with a bearer token ($JWT); $PROJECT_ID is the project UUID.
Create a project from a file
Section titled “Create a project from a file”# POST a .xml (or .mpp if MPXJ is installed) as multipart form-data (field: "file").# Optional "program" field assigns the new project to a program — requires program Admin.# Default upload cap 50 MB; configurable via MSPROJECT_MAX_UPLOAD_MB.curl -X POST \ -H "Authorization: Bearer $JWT" \ -F "file=@plan.xml" \ https://trueppm.example.com/api/v1/projects/import/msproject/# 202 Accepted:# {"queued": true, "project_id": "<uuid>", "import_request_id": "<uuid>"}The project shell is created synchronously (you get back a usable project_id); tasks import asynchronously via the same outbox path as import-into-existing. The worker overwrites the shell’s name and start_date from the file header once parsing succeeds. Parse failures stay terminal (DEAD ImportRequest, no retry), leaving the empty shell so you can retry the upload or delete the project.
Import a file into an existing project
Section titled “Import a file into an existing project”# POST a .mpp or .xml file as multipart form-data (field name: "file").# Requires project Admin.curl -X POST \ -H "Authorization: Bearer $JWT" \ -F "file=@plan.mpp" \ https://trueppm.example.com/api/v1/projects/$PROJECT_ID/import/msproject/# 202 Accepted: {"detail": "Import queued.", "import_request_id": "<uuid>"}The import runs asynchronously — a 202 means the file was accepted and queued, not
that parsing is finished. Imports are durable: if the task broker is briefly unavailable
the request stays queued and is picked up automatically within ~30 seconds.
Export a project
Section titled “Export a project”# GET MS Project XML (2003+). Requires project Member (viewer or above).curl -H "Authorization: Bearer $JWT" \ https://trueppm.example.com/api/v1/projects/$PROJECT_ID/export/msproject.xml \ -o project.xmlList recent imports (project history)
Section titled “List recent imports (project history)”# GET recent imports for a project, newest first. Member+ read.# Returns at most ~14 days' worth of activity; rows older than the configured# TRUEPPM_IMPORT_RETENTION_DAYS (default 7) are purged.curl -H "Authorization: Bearer $JWT" \ https://trueppm.example.com/api/v1/projects/$PROJECT_ID/imports/# 200 OK:# {# "results": [# {# "id": "<uuid>",# "filename": "cloud_migration.xml",# "status": "done",# "creates_project": true,# "requested_at": "2026-05-28T13:11:54Z",# "initiated_by": 17,# "initiated_by_username": "marcus",# "task_count": 28# }# ]# }task_count is read from the linked Celery task’s result summary, so it stays null until the import worker writes its summary (PENDING / DISPATCHED rows) and for parse failures (DEAD rows). initiated_by_username is null if the originating user was later deleted — the ImportRequest row survives the user purge.
Import formats
Section titled “Import formats”| Format | Extension | Parser | Notes |
|---|---|---|---|
| MS Project XML (2003+) | .xml | parse_xml | Preferred path; human-readable; supported by MS Project 2003–365, ProjectLibre, GanttProject, Primavera interop |
| MS Project XML (pre-2003) | .xml | parse_xml | Same parser; handles missing XML namespace |
| MS Project binary | .mpp | parse_mpp → parse_xml | Converted to XML by MPXJ CLI before parsing; requires Java 11+ and MPXJ_JAR_PATH |
XML field-coverage matrix
Section titled “XML field-coverage matrix”Project-level fields
Section titled “Project-level fields”| MS Project XML field | TruePPM field | Status |
|---|---|---|
<Name> | Project.name | ✅ Mapped |
<StartDate> | Project.start_date | ✅ Mapped |
<Title> | — | ⬜ Ignored |
<CreationDate> | — | ⬜ Ignored |
<FinishDate> | — | ⬜ Ignored |
<DefaultStartTime> | — | ⬜ Ignored |
<DefaultFinishTime> | — | ⬜ Ignored |
<MinutesPerDay> | — | ⬜ Ignored |
<MinutesPerWeek> | — | ⬜ Ignored |
<DaysPerMonth> | — | ⬜ Ignored |
<Calendars> | Calendar / CalendarException | ✅ Mapped |
<CalendarUID> | Project.calendar | ✅ Mapped |
<ExtendedAttributes> (PERT only) | three-point estimate mapping | ✅ Partial |
<OutlineCodes> | — | ⬜ Ignored |
Task-level fields
Section titled “Task-level fields”| MS Project XML field | TruePPM field | Status | Notes |
|---|---|---|---|
<UID> | internal mapping key | ✅ Required | UID 0 (project summary) is always skipped |
<Name> | Task.name | ✅ Required | Tasks missing a name are skipped with a warning |
<Duration> | Task.duration | ✅ Mapped | ISO 8601 duration; converted to working days at 8 h/day |
<OutlineNumber> | Task.wbs_path | ✅ Mapped | Dot-separated WBS code (e.g. 1.2.3) |
<OutlineLevel> | hierarchy depth | ✅ Mapped | Used for parent/child detection |
<Milestone> | Task.is_milestone | ✅ Mapped | 1 → is_milestone=True; milestone duration is always imported as 0 |
<PercentComplete> | Task.percent_complete | ✅ Mapped | Integer 0–100 (same scale both sides) |
<Notes> | Task.notes | ✅ Mapped | Free-text notes |
<Start> | Task.planned_start | ✅ Mapped | Date portion only; time component ignored |
<PredecessorLink>/<PredecessorUID> | Dependency.predecessor | ✅ Mapped | |
<PredecessorLink>/<Type> | Dependency.dep_type | ✅ Mapped | 0→FF, 1→FS, 2→SF, 3→SS |
<PredecessorLink>/<LinkLag> | Dependency.lag | ✅ Mapped | Tenths-of-minutes → working days (4800 = 1 day) |
<ID> | — | ⬜ Ignored | |
<Summary> | — | ⬜ Ignored | Summary status derived from WBS hierarchy |
<Finish> | — | ⬜ Ignored | Derived from start + duration after CPM |
<WBS> | — | ⬜ Ignored | Modern WBS field; OutlineNumber is used instead |
<GUID> | — | ⬜ Ignored | |
<CalendarUID> | — | 🟡 Partial | TruePPM has no per-task calendars. A task referencing a calendar other than the project calendar imports with a warning and is scheduled on the project calendar. |
<LagFormat> | — | ⬜ Ignored | Lag always interpreted as tenths-of-minutes |
<ExtendedAttribute> Duration1 | Task.optimistic_duration | ✅ Mapped | PERT Optimistic; FieldID 188743783. See Three-point / PERT estimates. |
<ExtendedAttribute> Duration2 | Task.most_likely_duration | ✅ Mapped | PERT Most Likely; FieldID 188743784. |
<ExtendedAttribute> Duration3 | Task.pessimistic_duration | ✅ Mapped | PERT Pessimistic; FieldID 188743785. |
<ExtendedAttribute> Duration4 | — | ⬜ Ignored | PERT-Expected formula slot; MS Project re-derives it on file open. |
<ExtendedAttribute> (other) | — | ⬜ Ignored | Cost / Text / Flag / Number / Date custom fields are not imported. |
Resource fields
Section titled “Resource fields”| MS Project XML field | TruePPM field | Status |
|---|---|---|
<UID> | internal mapping key | ✅ Required |
<Name> | Resource.name | ✅ Required |
<MaxUnits> | Resource.max_units | ✅ Mapped |
<GUID> | — | ⬜ Ignored |
<EmailAddress> | — | ⬜ Ignored |
<NTAccount> | — | ⬜ Ignored |
<CalendarUID> | — | ⬜ Ignored |
Assignment fields
Section titled “Assignment fields”| MS Project XML field | TruePPM field | Status |
|---|---|---|
<TaskUID> | TaskResource.task | ✅ Required |
<ResourceUID> | TaskResource.resource | ✅ Required |
<Units> | TaskResource.units | ✅ Mapped |
Duration encoding
Section titled “Duration encoding”MS Project XML stores duration as ISO 8601 strings. TruePPM converts to whole working days using an 8-hour working day:
| MS Project duration | Working days | Notes |
|---|---|---|
PT0H0M0S | 0 | Milestone (zero-duration task) |
PT8H0M0S | 1 | Standard 1-day task |
PT16H0M0S | 2 | 2-day task |
P3D | 3 | PnD format (less common) |
P1DT8H0M0S | 2 | Mixed days + hours |
Dependency type mapping
Section titled “Dependency type mapping”MS Project <Type> | TruePPM dep_type | Description |
|---|---|---|
0 | FF | Finish-to-Finish |
1 | FS | Finish-to-Start (default) |
2 | SF | Start-to-Finish |
3 | SS | Start-to-Start |
Unrecognized type values default to FS.
Working calendars
Section titled “Working calendars”The file’s <Calendars> block round-trips with TruePPM’s working calendars, so a plan built on holidays or a non-5×8 week (4×10s, etc.) keeps its dates after import instead of being rescheduled on the default Monday–Friday / 8-hour calendar.
On import, the base calendar selected by the project-level <CalendarUID> (or the file’s only base calendar, when the header omits the UID) becomes the project’s working calendar:
- Weekdays — each
<WeekDay>entry maps onto theCalendar.working_daysmask. Files that list all seven days (as MS Project itself writes) map exactly; sparse files only adjust the days they mention, starting from the Monday–Friday default. - Hours per day — TruePPM stores a single daily hour total, not shift times. Per-day
<WorkingTimes>collapse to the most common daily total across working days. Shift start/end times are not preserved. - Exceptions — non-working
<Exception>ranges (holidays, shutdowns) becomeCalendarExceptionrows, names included. Both the<TimePeriod>andEnteredStartDate/EnteredFinishDateencodings are read, as is the legacyDayType=0form. Exceptions that add working time (DayWorking=1, e.g. a make-up Saturday) cannot be represented and are skipped with a warning. - Library reuse — the calendar row is reused from the shared calendar library when an existing calendar has the same name and identical semantics (mask, hours, exception ranges); otherwise a new row is created. Repeated imports converge on one row.
- Overwrite policy — create-from-import treats the file’s calendar as authoritative. Import-into-existing keeps a project’s already-configured calendar and warns when the file’s calendar differs (imported dates may shift in that case).
- Degraded: per-task calendars (task
<CalendarUID>) — TruePPM schedules every task on the project calendar and warns once per referenced calendar. Per-resource calendars (IsBaseCalendar=0) are not imported.
On export, the project’s applied calendars are emitted as a single base calendar (UID 1) referenced by the project-level <CalendarUID>. Composable calendar layers have no MSPDI equivalent, so they are folded the same way the scheduler composes them — weekday masks AND-ed, exception ranges unioned — and each working day is written as one continuous shift starting at 08:00. The exported file schedules on the same non-working mask TruePPM computed.
Three-point / PERT estimates
Section titled “Three-point / PERT estimates”MS Project has no native PERT fields since 2013. The idiomatic storage — shared by Microsoft’s published guidance, MPXJ, and the third-party PPM ecosystem — is four aliased custom Duration fields:
| MS Project | Alias | TruePPM field |
|---|---|---|
Duration1 | Optimistic | Task.optimistic_duration |
Duration2 | Most Likely | Task.most_likely_duration |
Duration3 | Pessimistic | Task.pessimistic_duration |
Duration4 | PERT Expected (formula) | — (derived) |
TruePPM imports and exports this convention on both create-from-import and import-into-existing flows, and uses the values directly for Monte Carlo PERT-Beta sampling.
On import, TruePPM detects the PERT slots by their canonical numeric FieldIDs (sourced from MPXJ, not guessed; see ADR-0093 for the locked values and rationale). The alias text is treated as a confirmation: if the FieldID matches Duration1 but the alias contradicts (e.g. someone repurposed Duration1 as “Risk Score”), the binding is refused and a warning is added to the import summary. This protects Monte Carlo input from silent corruption when files reuse the slots for other purposes.
All-or-none. A task is imported with three-point values only when all three (Optimistic, Most Likely, Pessimistic) are present in the file. Partial data — e.g. Duration1 and Duration2 set but Duration3 missing — drops all three and emits a warning. This matches the scheduler engine’s invariant: PERT-Beta sampling requires all three.
Summaries and milestones are skipped in both directions. MS Project files conventionally leave Duration1–3 empty on these rows; if a file violates the convention, TruePPM still drops them to keep the round-trip stable.
estimate_status on import. Imported three-point values are written with estimate_status = "accepted" regardless of the project’s estimation_mode. The uploader holds project-admin permission and the values are PM-authored migration data, not contributor suggestions — re-approval per task under SUGGEST_APPROVE would be busywork.
Round-trip tolerance. Durations that are integer multiples of 8 hours round-trip losslessly. Non-multiples (e.g. PT23H) round down to the next lower working-day count on import; subsequent re-export emits the rounded value. This is the same tolerance the primary Duration field has had since the importer shipped.
On export, the four <ExtendedAttributes> definitions are emitted at project level (Duration4 carries the formula ([Duration1] + 4*[Duration2] + [Duration3]) / 6) only when at least one non-summary, non-milestone task has all three values set. Per-task <ExtendedAttribute> values are emitted for leaf work tasks. Re-opening the exported file in MS Project shows the four custom-field columns populated and Duration4 computed.
Resource matching
Section titled “Resource matching”When importing resources, TruePPM first searches for an existing Resource record with a name that matches case-insensitively. If a match is found the existing record is reused (no duplicate created). If no match exists, a new Resource record is created.
Import warnings
Section titled “Import warnings”The import summary includes a warnings list for non-fatal issues:
| Condition | Warning message |
|---|---|
| Task has no name | "Task UID {n}: missing name, skipped" |
| Dependency references an unknown predecessor | "Predecessor UID {n} not found, skipping dependency" |
| No tasks found in the file | "No tasks found in MS Project file" |
| PERT slot has a contradicting alias | "Project ExtendedAttribute FieldID {fid} has non-standard alias '{alias}'; three-point estimate ({role}) skipped" |
| Task has partial three-point data | "Task '{name}': partial three-point estimate (missing {fields}), all three values skipped" |
| Tasks reference a non-project calendar | "{n} task(s) reference calendar '{name}' (UID {uid}); TruePPM has no per-task calendars — they are scheduled on the project calendar" |
| Calendar exception adds working time | "Calendar '{name}': working-time exception '{exception}' is not supported and was skipped" |
| File calendar conflicts with the project’s configured calendar | "File calendar '{name}' differs from the project's configured calendar '{name}'; the project calendar was kept — imported dates may shift" |
Project CalendarUID not found among base calendars | "Project calendar UID {uid} not found among the file's base calendars; project calendar left unchanged" |
The import summary also includes two counts you can use to confirm three-point coverage at a glance:
tasks_with_three_point_estimates— leaf tasks that received all three values.tasks_skipped_partial_three_point— tasks for which the file supplied a subset (1 or 2 of the three values).
Export details
Section titled “Export details”TruePPM exports projects to MS Project XML 2003+ format. All tasks, dependencies, resources, and assignments are written. Fields exported per task:
UID, ID, Name, Duration (hours), Start, Finish, OutlineNumber, OutlineLevel, Milestone, PercentComplete, Notes, PredecessorLink (with Type and LinkLag), and the four PERT ExtendedAttribute values when three-point estimates are present (see above).
Resources: UID, ID, Name, MaxUnits.
Assignments: UID, TaskUID, ResourceUID, Units.
When the project has a working calendar applied, the export also writes the project-level CalendarUID and a <Calendars> block with the folded calendar — weekdays, working times, and exceptions (see Working calendars).
Configuration
Section titled “Configuration”Operator-facing configuration — upload size limit, the optional MPXJ / Java toolchain for .mpp import, the import-history retention window, and a quick reference to the security boundaries on parsed files — lives at MS Project configuration.
At a glance: the per-file upload cap defaults to 50 MB (MSPROJECT_MAX_UPLOAD_MB); .xml imports always work; .mpp imports need MPXJ_JAR_PATH and a Java 11+ runtime in the container; ImportRequest history rows are retained for 7 days by default (TRUEPPM_IMPORT_RETENTION_DAYS).