Task classification

Every task carries three classification fields — type, governance_class, and delivery_mode — that describe what kind of work it is, which overlay governs it, and how it executes and rolls up. They have always been part of the unified data model and are set by the demo seeds, but until now there was no way to change them from the task editor.

The task create/edit dialog will gain a Classification group with three selects — Type, Governance class, and Delivery mode — each with a one-line description of the selected value. The group is hidden when you create a milestone (a milestone is a zero-duration marker, not typed or governed work — its is_milestone flag is what matters there).

In 0.4, each of the three fields will also carry an info (ⓘ) button next to its label. Clicking it opens a short popover that lists every option for that field with its one-line meaning — so you can compare all the choices before you pick, rather than selecting each in turn to read its description — plus a Learn more link back to the relevant section of this page. The inline description of the current selection stays put; the popover is additive.

The controls are read-only for Viewers and non-owning Members; the server remains the authority on who may write each field.

type drives the board lane, the work-item badge, and whether the task carries schedulable effort.

TypeMeaning
TaskStandard unit of work with effort and dates. The default.
StoryA user-facing increment, estimated in story points.
BugA defect against accepted scope.
SpikeTime-boxed research; answers a question and ships no deliverable.
Tech DebtRefactoring or remediation work. Scheduled like a Task and counts toward velocity, but reported separately so a team can see how much capacity went to debt.
EpicA structural parent. It groups child work and rolls up — and it is excluded from CPM scheduling and every committed-delivery aggregate, exactly like a recurring template.

Epic is special: it changes hierarchy rather than adding schedulable work, so changing a task to or from epic is gated to the Product Owner or an Admin. If you do not hold that role, the editor surfaces the server’s refusal rather than silently dropping the change.

Tech Debt is the deliberate opposite of Epic: it is schedulable work that consumes sprint capacity, so it is not excluded from velocity — hiding it would understate a team’s real throughput. Its only distinct treatment is visibility. A tech-debt card will carry a Tech Debt badge on its board face (other types stay unbadged to keep the board calm), the board toolbar will gain a quiet Tech debt filter that narrows the board to remediation work, and any client can chart debt distinctly through the ?type=tech_debt task-list filter. Together these answer the recurring engineering question — how much of our capacity is going to debt versus features? — without removing that capacity from the numbers.

Governance class — which overlay governs the subtree

Section titled “Governance class — which overlay governs the subtree”

governance_class selects which governance model applies to a task and its subtree. It is distinct from delivery mode: governance is about oversight, delivery is about execution.

Governance classMeaning
FlowAgile work, governed by the sprint or kanban board.
GatedPhase-gate–governed waterfall work.
HybridMixes flow and gated within the same subtree.

Delivery mode — how the work executes and rolls up

Section titled “Delivery mode — how the work executes and rolls up”

delivery_mode selects how a task is executed, estimated, and rolled up. It is finer-grained than the project-level methodology preset: a single hybrid program can hold tasks in different delivery modes.

Delivery modeRolls up from
WaterfallExplicit percent-complete. Participates in CPM and the baseline.
ScrumStory-point burndown; velocity-tracked.
KanbanItem throughput (done / total) on a WIP-limited board.
MilestoneA zero-duration gate marking a date or phase.

Delivery mode is what the rollup engine reads to interpret a parent’s percent-complete — a Scrum subtree rolls up from burndown while a Waterfall subtree rolls up from explicit percent — so setting it correctly keeps a hybrid program’s rollups honest.

Creating a task pre-selects Governance class and Delivery mode from the project’s effective methodology (ships in 0.4) — the values a self-managing team would pick anyway, so the dialog never opens on a value that contradicts the project it belongs to:

Project methodologyGovernance class defaultDelivery mode default
WaterfallGatedWaterfall
AgileFlowScrum — or Kanban if the project’s board already runs continuous flow with no sprint cadence
HybridFlowWaterfall (unchanged — Hybrid is the preset that deliberately mixes both models)

The picker still lists every governance class and every delivery mode on every methodology — the taxonomy stays additive, so a Waterfall program can mark one compliance-sensitive subtree flow / scrum without losing anything, and a Hybrid program can mix freely as before. The methodology-consistent value(s) are simply listed first; the rest sit under an “Other” group in the same select, one click away.

The default is resolved server-side, in the task-create request, so web, mobile, and the MCP server agree — none of them re-implements the rule. It is a create-time default only: switching a project’s methodology later never rewrites the stored governance_class / delivery_mode on its existing tasks, and editing an existing task always shows what is actually stored, never a re-derived value.

A hybrid plan is usually declared a branch at a time, not a row at a time. On the Schedule, focus a row and press ⌘⇧M (Ctrl+Shift+M on Windows and Linux) — or right-click the row and choose Classification… — to open a popover that sets both axes for that task and, optionally, everything beneath it.

The popover has three rows:

  • PresetGated, Scrum, or Flow. Each writes both fields, which covers the common case in one click.
  • Governed by — the governance_class values above.
  • Progress from — the delivery_mode values above.

The two axis rows stay visible under the presets, so a blended team can say flow + kanban without being routed through Scrum vocabulary. Either axis can be left on No change — the cascade writes only what you name.

Section titled “The footer says what will happen before it happens”

Before you apply anything, the popover’s footer states the outcome: how many tasks change, how many milestones are left alone, and how many explicit governance overrides are preserved. Three of those numbers are worth understanding:

  • Milestones are never re-typed. is_milestone, delivery_mode = milestone, and duration = 0 are three encodings of one fact. Cascading an agile delivery mode across a phase skips every gate inside it and says so — a gate is not a delivery mode.
  • Your per-task edits survive by default. A task whose governance class was set explicitly (rather than inherited from its parent) keeps it, and the footer counts how many were kept. Clear Keep explicit governance overrides to cascade over them.
  • “Overrides kept” is a governance-only number. Only governance_class records whether a task inherited its value; delivery_mode carries no such flag, so no override count exists for it. The popover says that rather than showing a zero that would read as “there were none”.

After the cascade lands, a receipt names what the server actually wrote — not what the preview predicted — including any rows it skipped.

The toast that reports what the cascade wrote carries an Undo action. Applying it restores every changed task’s prior governance_class and delivery_mode — but only for rows nobody has reclassified again since. A row someone else recascaded, or that you changed again yourself, is left as it is rather than being stomped; the undo toast says how many it kept. Undo is a single step per cascade — undoing an older cascade once a newer one has landed on the same subtree is not supported.

A declared split is only useful if you can see it. On the Schedule outline, a task whose delivery mode is not the waterfall baseline carries two marks:

  • a 3px gutter at the left edge of the row, and
  • a mode chip beside the task name — SCRUM, KANBAN, or MIXED.

A summary row reads from its descendants, not from its own stored field, so a phase whose branches disagree reads MIXED and gets a gutter split between the modes actually present. Milestones inside it do not count toward the mix — otherwise nearly every phase in every plan would read mixed.

Waterfall draws neither mark. That is the same convention the Gantt already uses: the baseline is silent, so what stands out is the work that departs from it, and a fully gated plan stays visually calm. On the timeline, the same tasks carry a colored bar gutter and a fill texture (diagonal hatching for scrum, dots for kanban), with a legend entry naming each. Color is never the only signal — the chip states the mode in text, and the textures survive a monochrome print.

Nothing forks. Dependencies cross the boundary freely: a gated 4.1 still drives a sprint 4.2, on one plan and one timeline.

Where a subtree is driven by a sprint, the Schedule also paints the sprint’s window as a band across that subtree’s rows — the same violet and the same diagonal hatch, at a region’s scale. So the delivery mode says how the work executes and the band says when the cadence puts it, both on the timeline that already carries the gated critical path. See Sprint windows.

The three fields are the seam that lets one task hierarchy serve Waterfall, Agile, and Hybrid teams at once without translation. A program manager can mark a compliance subtree gated / waterfall while the team next to it runs flow / kanban, and both roll up into the same program view. Before the editor, that taxonomy could only be set through the seed data or the API; 0.3 puts it in front of the user.

  • Unified data model — the full Task field set these three fields belong to
  • Methodology preset — the project-level planning model, which delivery mode refines per task
  • Scheduler — how CPM consumes the schedulable fields (and skips epics)